HRERA GurugramTemp Project Id : RERA-GRG-PROJ-460-2019
Submission Date : 30-12-2019 05:00:38 AM
Applicant Type : Company
Project Type: ONGOING




M/S VATIKA SEVEN ELEMENTS PRIVATE LIMITED (FORMERLY KNOWN AS M/S STRONG INFRABUILD PVT. LTD.)
FLAT NO. 224A, 2ND FLOOR, DEVIKA TOWERS, 6, NEHRU PLACE, NEW DELHI - 110019
01244177777
9810566938 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
http://www.vatikagroup.com
XXXX626F
U70100DL2011PTC226157
 
 


 
 


 
 


 
 


 
 







SEVEN ELEMENTS (PHASE-I)
SECTOR-89 A, VILLAGE HARSARU AND HAYATPUR
HARSARU ST
GURUGRAM
0000000000
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
ARUP KUMAR DAS
0000000000
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
15693928-07-2017914000HDFC BANK LIMITEDHRERA Gurugram







57870.05 (Sqr/mtrs)
175
164.71
57870.05 (Sqr/mtrs)
41 of 2013 Dated 06.06.2013
No
Address     FLAT NO. 224A, 2ND FLOOR, DEVIKA TOWERS, 6, NEHRU PLACE, NEW DELHI - 110019
Address     VPO-RITHOJ, TEHSIL-SOHNA, DISTT.-GURUGRAM (HARYANA)
Address     VPO-RITHOJ, TEHSIL-SOHNA, DISTT.-GURUGRAM (HARYANA)
Annexure-B- COLLABORATION AGREEMENT, GPA, REVENUE RECORDS, ETC.
BEFORE GRANT OF LICENSE
Yes
PROVIDED
No
Yes
Yes







81536.00 Lakhs
18437.00 Lakhs
31651.41 Lakhs
1348.59 Lakhs
30099.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS12925.63
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS23431.30
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE740.57
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13CONSTRUCTION20137.158
Total57234.658




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/HSVPNo
WATER SUPPLYHUDA/HSVPNo
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDA/HSVPNo
STORM WATER DRAINAGEHUDA/HSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS364.12AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM107.89AS PER PROJECT REPORT
3STORM WATER DRAINAGE134.86AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM202.29AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL121.37AS PER PROJECT REPORT
6STREET LIGHTING80.91AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING26.97AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS67.43AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15STP80.91AS PER PROJECT REPORT
16RAIN WATER HARVESTING26.97AS PER PROJECT REPORT
17ELECTRICAL SUBSTATION134.86AS PER PROJECT REPORT


17-10-2014 (date)
17-10-2014 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type ANNEX-15 (DETAIL OF UNITS)6582.1258911647310






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
ANNEX-15 (DETAIL OF UNITS)116ANNEXURE-20 (DETAILS OF UNITS WITH CONSTRUCTION STAGE)


20-10-2014
31-01-2022
31-01-2022
11-01-2018
29
31-01-2022
PROVIDED
PROVIDED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
11-01-2018
0
31-01-2022
NOT APPLICABLE
NOT APPLICABLE


915
0
0
42
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments7560.29
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments450.00500.00
Shops00
Plots00

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments550.00600.00650.00752.83
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments73.31740.0549.82500.00
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments500.00500.00500.001000.00
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2000.002000.004000.004000.00
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4725.11
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements81.19
Water Supply System24.06
Sewerage treatment & garbage disposal27.06
Electricity Supply System45.10
Storm Water Drainage30.07
Parks and Playgrounds15.03
Clubhouse/community centres0
Shopping area0
Other0
Electrical Sub station30.07
Rain Water Harvesting6.01
Security and fire fighting6.01
STP18.04
Street lighting18.04

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.971.97
Water Supply System1.471.47
Sewerage treatment & garbage disposal1.001.00
Electricity Supply System1.761.76
Storm Water Drainage1.841.84
Parks and Playgrounds0.920.92
Clubhouse/community centres00
Shopping area00
Other00
Security and fire fighting0.370.37
STP0.101.10
Rain Water Harvesting0.370.63
Electrical Sub station0.101.84
Street lighting0.102.10

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.747.978.197.04
Water Supply System1.471.471.472.09
Sewerage treatment & garbage disposal1.002.003.292.35
Electricity Supply System2.763.024.503.91
Storm Water Drainage1.841.841.842.61
Parks and Playgrounds0.920.920.921.30
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical Sub station3.581.841.842.61
Street lighting1.101.101.101.57
Security and fire fighting0.370.370.370.52
STP2.101.101.101.57
Rain Water Harvesting0.110.370.370.52

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.037.142.636.08
Water Supply System0.602.110.781.80
Sewerage treatment & garbage disposal0.682.380.882.03
Electricity Supply System1.133.961.463.38
Storm Water Drainage0.752.640.972.25
Parks and Playgrounds0.381.320.491.13
Clubhouse/community centres0000
Shopping area0000
Other0000
STP0.451.590.581.35
Security and fire fighting0.150.530.190.45
Street lighting0.451.590.581.35
Electrical Sub station0.752.640.972.25
Rain Water Harvesting0.150.530.190.45

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.086.086.0812.15
Water Supply System1.801.801.803.60
Sewerage treatment & garbage disposal2.032.032.034.05
Electricity Supply System3.383.383.386.75
Storm Water Drainage2.252.252.254.50
Parks and Playgrounds1.131.131.132.25
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and fire fighting0.450.450.450.90
STP1.351.351.352.70
Street lighting1.351.351.352.70
Rain Water Harvesting0.450.450.450.90
Electrical Sub station2.252.252.254.50

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.3024.3048.6048.60
Water Supply System7.207.2014.4014.40
Sewerage treatment & garbage disposal8.108.1016.2016.20
Electricity Supply System13.5013.5027.0027.00
Storm Water Drainage9.009.0018.0018.00
Parks and Playgrounds4.504.509.009.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Street lighting5.405.4010.8010.80
Electrical Sub station9.009.0018.0018.00
Rain Water Harvesting1.801.803.603.60
STP5.405.4010.8010.80
Security and fire fighting1.801.803.603.60

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements57.00
Water Supply System16.89
Sewerage treatment & garbage disposal19.00
Electricity Supply System31.67
Storm Water Drainage21.11
Parks and Playgrounds10.56
Clubhouse/community centres0
Shopping area0
Other0
Electrical Sub station21.11
Security and fire fighting4.22
STP12.67
Rain Water Harvesting4.22
Street lighting12.67












Particulars Remarks, if any
i. No. of Flats/Apartments constructed589To be Constructed
ii. No. of Flats/ Apartments booked116
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter11486.52 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter5059.00 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter6427.52 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter6427.52 Lakhs
vii. Amount invested in the project upto the date of application37489.88 Lakhs
Land cost (If any)18437.00 Lakhs
Apartments7560.29 Lakhs
Infrastructure300.69 Lakhs
EDC/ Taxes Etc.11191.92 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession44046.12 Lakhs
(a) In respect of existing allottees8674.62 Lakhs
(b) In respect of rest of the project35371.50 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
5000.00 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 3194.30 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS364.1281.19
II. WATER SUPPLY SYSTEM107.8924.06
III. STORM WATER DRAINAGE134.8630.07
IV. ELECTRICITY SUPPLY SYSTEM202.2945.10
V. SEWAGE TREATMENT & GARBAGE DISPOSAL80.9118.04
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.67.4315.03
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM26.976.01
XVII. OTHER FACILITIES AS PER PROJECT REPORT364.1281.19









Yes
Yes
ICICI BANK LTD., DLF CITY GURUGRAM HARYANA.
017705009572
ICIC0000177
110229030
000177
1.) MR. Anil Bhalla Add:- Hyde Park, Prakrati Marg, Sultanpur Farms, Gadaipur, South Delhi, Delhi 110030. 2.) MR. Gautam Bhalla Add:- LCG05 PHB, The Laburnam, Nathupur (67),Nathupur Gurgaon, Gurgaon, Haryana 122002. 3.) Mr. Gaurav Bhalla Hyde Park, Prakrati Marg, Sultanpur Farms, Mehrauli, Gadaipur, South Delhi, Delhi 110030. 4.) MR. K.V. George Add:- Flat No. 1504, Mohinder Apartment, Plot No 17, Sector 12, Dwarka, South West Delhi, Delhi 110075. 5.) Mrs. Veena Bhomia Add:- C1/577B, Rear Block,1st Floor, Near Euro Kids School, Palam Vihar, Choma (62), Gurgaon, Haryana 122017.
Uploaded











Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LAY OUT PLANALREADY BEEN OBTAINED17-10-2014
II. ZONING PLANALREADY BEEN OBTAINED06-06-2013
III. BUILDING PLANALREADY BEEN OBTAINED17-10-2014
IV. SITE PLANALREADY BEEN OBTAINED17-10-2014
V. FLOOR PLANALREADY BEEN OBTAINED17-10-2014
VI. APARTMENT PLANSALREADY BEEN OBTAINED17-10-2014
VII. ELEVATION SECTIONALREADY BEEN OBTAINED17-10-2014
VIII. SERVICE ESTIMATEALREADY BEEN OBTAINED16-10-2015








Yes


Yes


Provided







NIL- THIS IS THE FIRST PROJECT OF THE COMPANY
0
0
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
000
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-01-2022
31-01-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEREFER SECTION BELOW
2WALL FINISHING DETAILSREFER SECTION BELOW
3KITCHEN DETAILSREFER SECTION BELOW
4BATHROOM FITTINGSREFER SECTION BELOW
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESREFER SECTION BELOW
7GLASS WORKREFER POINT 13
8ELECTRIC FITTINGSIS COMPLIANT MODULAR SWITCHES / SOCKETS, SWITCHGEAR AND DISTRIBUTION BOXES FROM STANDARD MAKES AND BRAND.
9CONDUCTING AND WIRING DETAILSIS COMPLIANT COPPER WIRING IN CONCEALED CONDUITS. ADEQUATE PROVISION FOR LIGHT POINTS, FAN POINTS, RECEPTACLES AND POWER POINTS IN ALL ROOMS.
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGEOVER-HEAD AND UNDERGROUND WATER STORAGE TANKS PROVIDED.
12LIFT DETAILSSPACIOUS ELEVATORS WITH PLEASING INTERIORS. PROVISION OF A STRETCHER LIFT IN ALL THE CORES.
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSALUMINUM OR UPVC FRAME WINDOWS WITH CLEAR GLASS.
14DOORSNA
14.1MAIN DOORSPOLISHED HARDWOOD FRAME WITH POLISHED VENEERED DOORS.
14.2INTERNAL DOORSPAINTED HARDWOOD FRAMES AND FLUSH DOORS.
15AIR CONDITIONINGINTELLIGENT AIR-CONDITIONING THROUGH ENERGY EFFICIENT VRV / VRF SYSTEMS IN ALL BEDROOMS AND LIVING ROOMS.
16ELECTRICAL FITTINGSREFER POINT 8
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE ANTI FUNGAL / ANTI ALGAL PAINT FROM REPUTED MAKES AND BRANDS.
20INTERNAL FINISHINGREFER SECTION BELOW.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORHIGH QUALITY, ABRASION RESISTANT MATT FINISHED VITREOUS CERAMIC TILES.
1 . 2 WALLSPREMIUM EMULSION PAINT ON PLASTERED WALL WITH PUNNING OR PUTTY FOR LEVEL AND SMOOTHNESS.
1 . 3 CEILINGOBD ON PLASTER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORHIGH QUALITY WOODEN FLOORING IN ALL BEDROOMS.
2 . 2 WALLSPREMIUM EMULSION PAINT ON PLASTERED WALL WITH PUNNING OR PUTTY FOR LEVEL AND SMOOTHNESS.
2 . 3 CEILINGOBD ON PLASTER
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORMATT FINISHED/ANTI-SKID CERAMIC TILES.
3 . 2 WALLSPREMIUM MATT FINISHED CERAMIC WALL TILES UP TO DADO LEVEL. PREMIUM EMULSION ON PLASTERED SURFACES ABOVE DADO LEVEL.
3 . 3 CEILINGOBD ON PLASTER
3 . 4 COUNTERSGRANITE COUNTER TOP
3 . 5 SANITARY WARE/CP FITTINGSWASH BASIN AND EUROPEAN WATER CLOSET (EWC) OF REPUTED MAKES AND BRANDS.
3 . 6 FITTING/FIXTURESSINGLE LEVER BASIN MIXER, CONCEALED SHOWER MIXER / DIVERTER WITH BATH SPOUT AND OVERHEAD SHOWER, HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES ETC. OF REPUTED MAKES AND BRANDS.
4 . BED ROOMS
4 . 1 FLOORHIGH QUALITY WOODEN FLOORING IN ALL BEDROOMS.
4 . 2 WALLSPREMIUM EMULSION PAINT ON PLASTERED WALL WITH PUNNING OR PUTTY FOR LEVEL AND SMOOTHNESS.
4 . 3 CEILINGOBD ON PLASTER
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORMATT FINISHED/ANTI-SKID CERAMIC TILES.
5 . 2 WALLSPREMIUM MATT FINISHED CERAMIC WALL TILES UP TO DADO LEVEL. PREMIUM EMULSION ON PLASTERED SURFACES ABOVE DADO LEVEL.
5 . 3 CEILINGOBD ON PLASTER
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSWASH BASIN AND EUROPEAN WATER CLOSET (EWC) OF REPUTED MAKES AND BRANDS.
5 . 6 FIXTURESSINGLE LEVER BASIN MIXER, CONCEALED SHOWER MIXER / DIVERTER WITH BATH SPOUT AND OVERHEAD SHOWER, HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES ETC. OF REPUTED MAKES AND BRANDS.
6 . KITCHEN
6 . 1 FLOORMATT FINISHED CERAMIC TILES.
6 . 2 WALLS2’ HIGH CERAMIC TILES DADO ABOVE COUNTER. PREMIUM EMULSION ON PLASTER IN REMAINING AREAS. THE KITCHEN SHALL BE FITTED WITH FULLY FURNISHED MODULAR CABINETS IN AESTHETICALLY PLEASING FINISHES.
6 . 3 CEILINGOBD ON PLASTER
6 . 4 COUNTERSGRANITE COUNTERTOP
6 . 5 FIXTURESA DOUBLE BOWL SINK WITH MIXER WILL BE PROVIDED.
6 . 6 KITCHEN APPLIANCESA COOKTOP & A CHIMNEY INSTALLATION WILL BE PROVIDED.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORFLOOR FINISHES FOR SERVANT’S ROOM - MATT FINISHED / ANTI SKID CERAMIC TILES
7 . 2 WALLS & CEILINGWALL FINISHES FOR SERVANT’S ROOM - PAINT ON PLASTER.
7 . 3 TOILETFLOORING - MATT FINISHED CERAMIC TILES. WALL FINISHES - DADO OF GLAZED / MATT FINISHED CERAMIC WALL TILES. (PAINT ON PLASTERED SURFACES ABOVE DADO LEVEL FOR REMAINING AREAS). SANITARY WARE - WASH BASIN AND EUROPEAN WATER CLOSET (EWC) OF STANDARD MAKES. C.P. FITTINGS AND ACCESSORIES - BIB COCK, PILLAR COCK, ABLUTION TAP ALONG WITH NECESSARY ANGLE VALVES ETC. OF STANDARD MAKES AND BRANDS.
7 . 4 BALCONYFLOORING - MATT FINISHED / ANTI SKID CERAMIC TILES WALL FINISHES - EXTERIOR GRADE PAINT ON PLASTER.
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT20-02-2020 View Document
2LOI - 14-30 ACRES20-02-2020 ------
3SITE PLAN20-02-2020 ------
4DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.20-02-2020 View Document
5FOREST NOC20-02-2020 ------
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT20-02-2020 View Document
7LC-IV-14.30 ACRES20-02-2020 ------
8AAI CERTIFICATE20-02-2020 ------
9FIRE SCHEME20-02-2020 ------
10DETAILS OF SEPARATE BANK ACCOUNT04-03-2020 ------
11COPY OF LICENSE ALONG WITH SCHEDULE OF LAND11-12-2019 View Document
12SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN11-12-2019 View Document
13ZONING PLAN11-12-2019 View Document
14IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN11-12-2019 View Document
15A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS11-12-2019 View Document
16IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN11-12-2019 View Document
17TA2 A3 AREA CALCULATION ALL FLOOR30-12-2019 ------
1812 REVENUE RECORDS SALE DEED ETC30-12-2019 ------
1915 DETAIL OF UNITS FOR SEVEN ELEMENTS (PHASE-I)30-12-2019 ------
20BALANCE SHEET30-12-2019 ------
2116 DETAIL OF PARKING30-12-2019 ------
2211 AKS SHEJRA WITH LAND DETAILS30-12-2019 ------
2323 SPECIFICATION BR-II30-12-2019 ------
2424 BOOKING APPLICATION FORM -RESIDENTIAL FINAL30-12-2019 ------
2526 HRERA - AFS RESIDENTIAL - APARTMENT FINAL30-12-2019 ------
26RETAIL GF TERRACE PLAN EWS ELE SEC GURAD ROOM30-12-2019 ------
27EWS GF TO 5TH TERRACE PLAN AREA CALCULATION30-12-2019 ------
28MIDRISE BLOK SOUTH ELEVATION30-12-2019 ------
2925 ALLOTTMENT LETTER-RESIDENTIAL30-12-2019 ------
30SHAREHOLDERS30-12-2019 ------
31BOARD RESOLUTION (AUTHORISED SIGNATORIES BANKING30-12-2019 ------
32REP-I30-12-2019 ------
3321 LIST OF ARCHITECT ENGINEER ETC30-12-2019 ------
34PAN CARD30-12-2019 ------
35MIDRISE BLOK NORTH ELEVATION30-12-2019 ------
36MIDRISE BLOK SECTION 1 230-12-2019 ------
37MOA AND AOA30-12-2019 ------
3817 TIME PERIOD COMMITED TO ALLOTTEE30-12-2019 ------
39 LOCATION PLAN30-12-2019 ------
4010 SECTORIAL MAP30-12-2019 ------
4114 IDW DESIGN AND COST ESTIMATES30-12-2019 ------
42ANNEXURE 1 PROJECT DESCRIPTION AND COST30-12-2019 ------
43ANNEXURE 3 330-12-2019 ------
4417 ARCHITECT AND ENGINEER CERTIFICATE30-12-2019 ------
4518 CA CERTIFICATE30-12-2019 ------
46TA4 SECTION AA30-12-2019 ------
4719 CA CERTIFICATE30-12-2019 ------
48RETAIL GF TERRACE PLAN ELE SEC AREA CALCULATION30-12-2019 ------
49COLLECTION STATEMENT30-12-2019 ------
50MIDRISE BLOK 1ST TO 6 TH AREA CALCULATION30-12-2019 ------
5129 ADVERTISEMENT30-12-2019 ------
52NURSARY SCHOOL GF FF SEC ELE AREA CALCULATION30-12-2019 ------
53SCHEMATIC DIAGRAM T A2 A3 A430-12-2019 ------
5413 APPROVAL OF SERVICE PLAN OR ESTIMATE FOR GH30-12-2019 ------
55T A2 A3 ELEVATION 3 430-12-2019 ------
56T A2 A3 SECTION AA30-12-2019 ------
57T A4 AREA CALCULATION ALL FLOOR30-12-2019 ------
58TA4 ELEVATION 3 430-12-2019 ------
59MIDRISE BLOK 1ST FLOOR PLAN30-12-2019 ------
60MIDRISE BLOK 2 ND TO 6TH FLOOR PLAN30-12-2019 ------
61MIDRISE BLOK 8TH FLOOR PLAN30-12-2019 ------
62MIDRISE BLOK LMR B1 B2 FLOOR PLAN30-12-2019 ------
63REGISTRATION CERTIFICATE30-12-2019 ------
64RESOLUTION30-12-2019 ------
6527 CONVEYANCE DEED- RESIDENTIAL FINAL30-12-2019 ------
66T A4 GF TO 18TH TERRACE ROOF FLOOR PLAN30-12-2019 ------
67MIDRISE BLOK LMR B2 B3 FLOOR PLAN30-12-2019 ------
6828 SANCTION LETTER AND HOME LOAN TIE-UPS30-12-2019 ------
69MIDRISE BLOK 7TH FLOOR PLAN30-12-2019 ------
70TA2 A3 ELEVATION 1 230-12-2019 ------
71MIDRISE BLOK 7TH TO 8 TH AREA CALCULATION30-12-2019 ------
7215 DETAIL OF UNITS FOR SEVEN ELEMENTS (PHASE-I)30-12-2019 ------
73MIDRISE BLOK GF FLOOR PLAN30-12-2019 ------
7420 ENCUMBRANCES30-12-2019 ------
7522 DEVELOPMENT WORK PLAN30-12-2019 ------
76T A2 A3 GF TO 20TH TERRACE FLOOR PLAN30-12-2019 ------
77MIDRISE BLOK GF AREA CALCULATION30-12-2019 ------
78LIST OF DIRECTORS30-12-2019 ------
79SCHEMATIC DIAGRAM TIOLET KITCHEN DETAIL EWS MIDRISE BLOCK30-12-2019 ------
80T A4 ELEVATION 1 230-12-2019 ------
81NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT20-02-2020 View Document
82ENVIROMENTAL CLEARANCE20-02-2020 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 PROJECT CONTINUATION- RC/REP/HARERA/GGM/281 OF 2017/7(3)/39/2023/16 DATED 24.11.2023 12-12-2023 View Document