EMAAR BUSINESS PARK, MG ROAD, SIKANDERPUR, SECTOR-28, GURUGRAM, HARYANA-122002
01244421155
9811535184 (Number Shared by Promoter in Public)
coordination@emaar-india.com
http://www.emaar-india.com
XXXX308B
U45201DL2005PLC13316
PALM SELECT
SECTOR 77 SHIKHOPUR GURUGRAM
GURGAON
GURUGRAM
01244421155
2444211553 (Number Shared by Promoter in Public)
coordination@emaar-india.com
MR KETAN LUTHRA
01244421155
7838401624 (Number Shared by Promoter in Public)
ketan.luthra@emaar-india.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
202522
25-10-2019
291750
HSBC
HRERA Gurugram
2
202967
13-12-2019
162170
HSBC
HRERA Gurugram
3.29 (Acre)
175
175
29.34675 (Acre)
56 of 2009 62 of 2013
No
Address NEEMRANA DEVELOPERS PVT. LTD. AND OTHERS
Annexure-B- COLLABORATOR
BEFORE GRANT OF THE LICENSE
No
NA
No
Yes
Yes
4046 Lakhs
36 Lakhs
2932 Lakhs
554 Lakhs
524 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.23
3
CONSTRUCTION OF ROADS
0.43
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.43
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
2.2
Total
3.29
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
ALREADY CONNECTED
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
88.61002
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
74.92165
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
29.11776
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
38.32854
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
41.56509
SUBMITTED TO HUDA
6
STREET LIGHTING
1.6211
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
2.802695
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
35.76688
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
9
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
PARKING
100
YET TO BE PREPARED
16
RAIN WATER HARVESTING
54
YET TO BE PREPARED
17
ELECTRIC SUB STATION
67
YET TO BE PREPARED
28-08-2015 (date)
23-10-2018 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B12- 3 BHK
96.042
22
0
22
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B13- 3 BHK
96.042
22
0
22
1
3
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B14- 3 BHK
96.042
22
0
22
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
TOWER B12- 3 BHK
0
0
TOWER B13- 3 BHK
0
0
TOWER B14- 3 BHK
0
0
28-02-2011
31-12-2022
31-12-2022
28-02-2011
60
31-12-2022
THE PROJECT IS NEARING COMPLETION. CIVIL WORK IS COMPLETED & FINISHING WORK IS IN PROGRESS
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
28-02-2011
0
31-12-2022
0
15
84
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
1414
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
1456
Shops
0
Plots
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
100
373
Shops
0
0
Plots
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
455
277
304
209
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
125
96
73
66
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
38
Water Supply System
33
Sewerage treatment & garbage disposal
16
Electricity Supply System
15
Storm Water Drainage
12
Parks and Playgrounds
14
Clubhouse/community centres
0
Shopping area
0
Other
0
Electric Sub Station
23
Parking
45
Rain Water Harvesting
24
Renewable Energy System
5
Security
1
Street Light
6
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10
20
Water Supply System
0
20
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
4
Parks and Playgrounds
0
12
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Security
2
0
Street Light
6
0
Renewable Energy System
0
5
Parking
0
9
Electric Sub Station
0
0
Rain Water Harvesting
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11
10
0
0
Water Supply System
10
10
2
0
Sewerage treatment & garbage disposal
0
0
5
5
Electricity Supply System
0
5
5
5
Storm Water Drainage
6
4
3
1
Parks and Playgrounds
5
5
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Electric Sub Station
22
0
0
9
Parking
20
10
10
0
Rain Water Harvesting
11
8
11
0
Security
0
0
0
0
Street Light
0
0
0
0
Renewable Energy System
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
5
5
5
0
Electricity Supply System
5
3
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Parking
3
3
Electric Sub Station
0
12
Renewable Energy System
0
Rain Water Harvesting
0
Security
0
Street Light
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
66
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
1646 Lakhs
Land cost (If any)
0 Lakhs
Apartments
1225 Lakhs
Infrastructure
232 Lakhs
EDC/ Taxes Etc.
186 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
2400 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
2400 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
88.61002
38
II. WATER SUPPLY SYSTEM
74.92165
33.3
III. STORM WATER DRAINAGE
29.11776
11.6
IV. ELECTRICITY SUPPLY SYSTEM
38.32854
15
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
41.56509
16.4
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
35.77
14
XIII. COVERED PARKING
100
45
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
2.80
0.75
XVII. OTHER FACILITIES AS PER PROJECT REPORT
142.6211
57.95
Yes
Yes
HDFC BANK, K G MARG - BRANCH LOCATED AT 209 - 214, KAILASH BUILDING, 26, KASTURBA GANDHI MARG, NEW DELHI 110001.
57500000360473
HDFC0000003
110240001
209 - 214
Rahul Bindle,
E303, Park view City 1,
Sector 48, Sohna Road, gurugram
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. SERVICE PLAN ESTIMATES APPROVAL
ALREADY BEEN OBTAINED
17-11-2016
II. ENVIRONMENT CLEARANCE APPROVAL BASED ON LATEST APPROVED BUILDING PLAN
ALREADY BEEN OBTAINED
09-10-2024
III. FOREST NOC
ALREADY BEEN OBTAINED
09-02-2015
IV. FIRE SCHEME APPROVAL
ALREADY BEEN OBTAINED
19-04-2017
V. ZONING PLAN APPROVAL
ALREADY BEEN OBTAINED
18-11-2010
VI. ZP-567/AD(RA)/2015/16319
ALREADY BEEN OBTAINED
27-07-2022
VII. ZP-567/AD(RA)/2018/3008
ALREADY BEEN OBTAINED
22-11-2023
VIII. LICENSE NO. 62 OF 2013 VIDE ENDST. NO. LC-1031-III-JE(S)-2013/48446
APPLIED FOR BUT YET TO RECEIVE
04-08-2021
IX. LICENSE NO.56 OF 2009 VIDE ENDST. NO. 5DP-III-2009/9147
APPLIED FOR BUT YET TO RECEIVE
04-08-2021
X. AIRPORT HEIGHT CLEARANCE
APPLIED FOR BUT YET TO RECEIVE
01-05-2019
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: