HRERA GurugramTemp Project Id : RERA-GRG-PROJ-435-2019
Submission Date : 06-12-2019 04:55:22 AM
Applicant Type : Individual
Project Type: ONGOING




MAHENDER KUMAR GUPTA
DAYA NAND GUPTA
01129531296
 (Number Shared by Promoter in Public)
chairman@kpdkbuildtech.com
HTTP://WWW.KPDKBUILDTECH.COM
XXXX651E
_______________









NEWTOWN SQUARE
SECTOR-95A, MAIN PATAUDI ROAD, HYATPUR VILLAGE, GURUGRAM
GURGAON
GURUGRAM
01242276470
9810312799 (Number Shared by Promoter in Public)
nishant@kpdkbuildtech.com
NISHANT GUPTA
01242276470
9810312799 (Number Shared by Promoter in Public)
nishant@kpdkbuildtech.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150036026-07-2017498000ICICI BANKHRERA Gurugram
22090147633128-12-2018249000ICICI BANKHRERA Gurugram







3.075 (Acre)
1.87
1.8265
3.075 (Acre)
98 of 2013
Yes







13777 Lakhs
1132.23 Lakhs
7096 Lakhs
463.23 Lakhs
5085.64 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS4000
3CONSTRUCTION OF ROADS1500
4PAVEMENTS700
5PARKS AND PLAYGROUNDS500
6GREEN BELTS1000
7VEHICLE PARKINGS450
8ELECTRICITY SUB-STATION200
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY95
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13RAIN50
14BALANCE3949
Total12444




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNHAINo
WATER SUPPLYOFFICE OF EXECUTIVE ENGINEER HUDA GURGAONYes
ELECTRICITYDAKSHIN HARYANA BIJLI VITRAN NIGAMYes
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS166.34SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM171.17SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE34.13SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL27.49SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING11.78SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING8.72SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS0SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0SUBMITTED TO TOWN & COUNTRY PLANNING
13HOSPITAL/DISPENSARY0SUBMITTED TO TOWN & COUNTRY PLANNING
14ANY OTHER0SUBMITTED TO TOWN & COUNTRY PLANNING
15STP20SUBMITTED TO TOWN & COUNTRY PLANNING
16UNDERGROUND WATER TANK12.95SUBMITTED TO TOWN & COUNTRY PLANNING
17RAINWATER HARVESTING7.50SUBMITTED TO TOWN & COUNTRY PLANNING
18HORTICULTURE3.15YET TO BE PREPARED


19-09-2019 (date)
19-09-2019 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL SHOPS, SERVICE APARTMENTS AND OTHER COMMERCIAL AREA 19.07.201740004962302661
2APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL SHOPS, SERVICE APARTMENTS AND OTHER COMMERCIAL AREA ON 30.11.201904963001961






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
COMMERCIAL SHOPS, SERVICE APARTMENTS AND OTHER COMMERCIAL AREA AS ON 19.07.17230COMPLETE IN ALL RESPECTS AND OC APPLIED
SOLD AS ON 30.11.2019300COMPLETE IN ALL RESPECTS AND OC APPLIED
UNSOLD AS ON 30.11.2019196COMPLETE IN ALL RESPECTS AND OC APPLIED


09-06-2015
08-11-2019
30-11-2019
09-06-2015
85
30-11-2019
COMPLETED AND OC APPLIED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT2300 COMPLETED AND OC APPLIED
09-06-2015
80
30-11-2019


407
0
0
15
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00
Commercial6609.23580.44

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
COMMERCIAL COMPLEX390.51256.54247.48468.73

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00
COMMERCIAL COMPLEX0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
ADMIN EXP268.65
CONSTRUCTION2903.45
EDC IDC648.31
FINANCIAL EXP837.52
LAND COST1132.23
LEGAL EXP68.76
LICENCE ETC30.65
MARKETING ETC719.66

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Under Ground Tank12.95

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements012.548.4
Water Supply System2142.568.3
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements53221515.44
Water Supply System23106.370
Sewerage treatment & garbage disposal20207.490
Electricity Supply System0000
Storm Water Drainage24100.130
Parks and Playgrounds0003.15
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light Etc101.78
Rain Water Harvesting70.5
Fire Fighting System53.72












Particulars Remarks, if any
i. No. of Flats/Apartments constructed496
ii. No. of Flats/ Apartments booked230
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter7173.58 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter5124.07 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2049.51 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application4715 Lakhs
Land cost (If any)1132 Lakhs
Apartments2835 Lakhs
Infrastructure69 Lakhs
EDC/ Taxes Etc.679 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession9062 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project9062 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
3054 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 3193 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS166.340
II. WATER SUPPLY SYSTEM171.170
III. STORM WATER DRAINAGE34.130
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL47.490
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER11.780
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.3.150
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM8.720
XVII. OTHER FACILITIES AS PER PROJECT REPORT20.450









Yes
Yes
UNION BANK OF INDIA, KAILASH COLONY, NEW DELHI
355701011020715
UBIN0535575
110026019
535575
MR. VIKAS GUPTA 122A/20, GAUTAM NAGAR, NEW DELHI - 110049
ATTACHED IN FOLDER - D











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE FROM DTCP HARYANAALREADY BEEN OBTAINED06-03-2018
II. REVISED BUILDING PLANS APPROVAL FROM CHIEF TOWN PLANNER HARYANAALREADY BEEN OBTAINED19-09-2019
III. NOC FOR CONSTRUCTION FROM OFFICE OF THE ADMINISTRATOR HUDA GURGAONALREADY BEEN OBTAINED22-01-2014
IV. HEIGHT CLEARANCE FROM AAIALREADY BEEN OBTAINED16-07-2019
V. CLEARANCE FROM FOREST DEPARTMENTALREADY BEEN OBTAINED15-07-2014
VI. NOC FOR ARAVALI PROJECT PLANTATIONALREADY BEEN OBTAINED21-07-2014
VII. ASSURANCE FOR POWER SUPPLY FROM DHBVNALREADY BEEN OBTAINED11-11-2014
VIII. ASSURANCE OF WATER SUPPLY FOR DRINKING WATERALREADY BEEN OBTAINED13-11-2014
IX. PERMIT FOR MINING EXCAVATIONALREADY BEEN OBTAINED30-01-2015
X. CLEARANCE FROM NATIONAL BOARD OF WILDLIFEALREADY BEEN OBTAINED04-12-2014
XI. RENEWAL OF ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED10-10-2019
XII. CONSENT TO ESTABLISH FROM HARYANA STATE POLLUTION CONTROL BOARDALREADY BEEN OBTAINED16-04-2018
XIII. NOC FOR CONSTRUCTION OF RAINWATER HARVESTING STRUCTUREALREADY BEEN OBTAINED09-05-2018
XIV. APPROVAL OF FIRE FIGHTING SCHEMEALREADY BEEN OBTAINED30-10-2019
XV. OCCUPATION CERTIFICATEAPPLIED FOR BUT YET TO RECEIVE27-09-2019








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGRANITE STONE FOR STAIRCASE, LOBBY, CORRIDOR & PUBLIC AREA KOTA STONE FOR SERVICE ROOM VITRIFIED + CERAMIC TILES FOR BATHROOMS & MISCELLANEOUS AREA
2WALL FINISHING DETAILSCEMENT PLASTER + OBD + ENAMEL PAINT + WHITE WASH IN MISCELLANEOUS AREA
3KITCHEN DETAILSN.A.
4BATHROOM FITTINGSWATER CONSERVATORY FITTINGS AS PER GRIHA APPROVAL
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESRED MARANDI FRAME FOR NORMAL DOOR + PAINT + POLISH 2ND CLASS TEAK WOOD FOR FIRE DOOR FRAME + PAINT + POLISH WINDOW FRAME – POWDER COATED ALUMINIUM + UPVC
7GLASS WORK10MM THICK GLASS - RAILING 12MM THICK GLASS – RETAIL SHOPS 6T+12AG + 6T (DS40 – GUARDIAN GLASS) – EXTERNAL WINDOW 6T+12AG + 5T (DS40 – GUARDIAN GLASS) – EXTERNAL WINDOW
8ELECTRIC FITTINGSISI MARKED STANDARD FITTINGS
9CONDUCTING AND WIRING DETAILSISI MARKED STANDARD FITTINGS
10CUPBOARD DETAILSN.A.
11WATER STORAGEUG TANK – 670 KLD OH TANK – 110 KLD
12LIFT DETAILS9 LIFTS (20PAX#7 LIFT + 10PAX#2 LIFT)
13EXTERNAL GLAZINGSFOR WINDOWS
13.1WINDOWS/GLAZINGS6T+12AG + 6T (DS40 – GUARDIAN GLASS) 6T+12AG + 5T (DS40 – GUARDIAN GLASS)
14DOORSN.A.
14.1MAIN DOORSN.A.
14.2INTERNAL DOORSN.A.
15AIR CONDITIONINGN.A.
16ELECTRICAL FITTINGSISI MARKED STANDARD FITTINGS
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYN.A.
19EXTERNAL FINISHING/COLOUR SCHEMERUSTIC + SUPERFINE TEXTURE + ACRYLIC DISTEMPER PAINT – COLOR OAK LEAF BROWN SHADE, ICELAND WHITE SHADE GRANITE STONE CLADDING
20INTERNAL FINISHINGN.A.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN.A.
1 . 2 WALLSN.A.
1 . 3 CEILINGN.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN.A.
2 . 2 WALLSN.A.
2 . 3 CEILINGN.A.
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORN.A.
3 . 2 WALLSN.A.
3 . 3 CEILINGN.A.
3 . 4 COUNTERSN.A.
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A.
4 . BED ROOMS
4 . 1 FLOORN.A.
4 . 2 WALLSN.A.
4 . 3 CEILINGN.A.
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORN.A.
5 . 2 WALLSN.A.
5 . 3 CEILINGN.A.
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A.
5 . 6 FIXTURESN.A.
6 . KITCHEN
6 . 1 FLOORN.A.
6 . 2 WALLSN.A.
6 . 3 CEILINGN.A.
6 . 4 COUNTERSN.A.
6 . 5 FIXTURESN.A.
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A.
7 . 2 WALLS & CEILINGN.A.
7 . 3 TOILETN.A.
7 . 4 BALCONYN.A.
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSN.A.
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1KPDK BANK ACCOUNT DETAILS19-02-2020 ------
2FOLDER - D06-12-2019 ------
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN06-12-2019 View Document
4CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT06-12-2019 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT06-12-2019 View Document
6DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD06-12-2019 View Document
7ZONING PLAN06-12-2019 View Document
8DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.06-12-2019 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS06-12-2019 View Document
10CASH FLOW STATEMENT OF THE PROPOSED PROJECT06-12-2019 View Document
11FOLDER - F06-12-2019 ------
12COPY OF LICENSE ALONG WITH SCHEDULE OF LAND06-12-2019 View Document
13IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN06-12-2019 View Document
14SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN06-12-2019 View Document
15DEMARCATION PLAN06-12-2019 View Document
16FOLDER - C06-12-2019 ------
17FOLDER - E06-12-2019 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 Extension No. HARERA/GGM/REP/RC/192/ 2O17/EXT/101/2019 DATED-08.05.2019 28-05-2020 View Document
2 Occupation certificate received dated 04.08.2020 28-12-2022 View Document
3 Oc uploaded 04-08-2023 View Document
4 OC uploaded 08-08-2023 View Document