HRERA GurugramTemp Project Id : RERA-GRG-PROJ-415-2019
Submission Date : 28-12-2019 11:55:56 AM
Applicant Type : Company
Project Type: ONGOING




ORRIS INFRASTRUCTURE PRIVATE LIMITED
C-3/260, JANAKPURI, NEW DELHI-110058
01244979200
9560099004 (Number Shared by Promoter in Public)
info@orris.in
http://www.orris.in/
XXXX494P
U70109DL2006PTC151295
 
 


 
 


 
 


 
 







ASTER COURT PREMIER
SECTOR - 85, VILLAGE- BADHA , TEHSIL-MANESAR, GURUGRAM
MANESAR
GURUGRAM
1244979200
9717396016 (Number Shared by Promoter in Public)
info@orris.in
SANJAY SINGH
01244979200
9717396016 (Number Shared by Promoter in Public)
sanjay.singh@orris.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150597601-08-2018760500ICICI BANKHRERA Gurugram







5.90625 (Acre)
1.75
1.75
29.068 (Acre)
39 OF 2009 (24.07.2009), 99 OF 2011 (17.11.2011)
No
Address     ADDRESS
Address     ADDRESS
Address     ADDRESS
Address     ADDRESS
Address     ADDRESS
Address     ADDRESS
Annexure-B- COLLABORATOR
BEFORE GRANT OF LICENCE
Yes
POWER OF ATTORNEY REGISTERED WITH THE REGISTRAR AT GURUGRAM/MANESAR
No
Yes
Yes







30515.76 Lakhs
478.70 Lakhs
19542 Lakhs
2031 Lakhs
8463.3 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.016
3CONSTRUCTION OF ROADS1.579
4PAVEMENTS0.175
5PARKS AND PLAYGROUNDS1.610
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0.201
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER1.325
Total5.906




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSPWDYes
WATER SUPPLYNo
ELECTRICITYDAKSHIN HARYANA BIJLI NIGAMYes
SEWAGE DISPOSALNo
STORM WATER DRAINAGENo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS473.30YET TO BE PREPARED
2WATER SUPPLY SYSTEM60.92YET TO BE PREPARED
3STORM WATER DRAINAGE50.02YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM579.00YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING82.53YET TO BE PREPARED
8PLAYGROUNDS AND PARKS12.36YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE350YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER423.18YET TO BE PREPARED


10-04-2012 (date)
10-04-2012 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3K (3BHK+S)115.2221661
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3L(3BHK+S)115.2207131
3APARTMENT/SHOPS/OTHER BUILDINGS Type 3M(3BHK+S)115.2201191
4APARTMENT/SHOPS/OTHER BUILDINGS Type 3N(3BHK+S)115.2221751
5APARTMENT/SHOPS/OTHER BUILDINGS Type 3O(3BHK+S)115.2209111
6APARTMENT/SHOPS/OTHER BUILDINGS Type 3P(3BHK+S)115.2221661
7APARTMENT/SHOPS/OTHER BUILDINGS Type 4A(4BHK+S)140.6221661
8APARTMENT/SHOPS/OTHER BUILDINGS Type 4B(4BHK+S)140.6241951
9APARTMENT/SHOPS/OTHER BUILDINGS Type 4C(4BHK+S)140.6220221
10APARTMENT/SHOPS/OTHER BUILDINGS Type 4D(4BHK+S)140.6222201
11APARTMENT/SHOPS/OTHER BUILDINGS Type 4E(4BHK+S)140.62414101
12APARTMENT/SHOPS/OTHER BUILDINGS Type 4F(4BHK+S)140.62211111






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
3K (3BHK+S)16FINISHING WORK IN PROGRESS
3L(3BHK+S)7FINISHING WORK IN PROGRESS
3M(3BHK+S)1FINISHING WORK IN PROGRESS
3N(3BHK+S)17FINISHING WORK IN PROGRESS
3O(3BHK+S)9FINISHING WORK IN PROGRESS
3P(3BHK+S)16FINISHING WORK IN PROGRESS
4A(4BHK+S)16FINISHING WORK IN PROGRESS
4B(4BHK+S)19FINISHING WORK IN PROGRESS
4C(4BHK+S)0FINISHING WORK IN PROGRESS
4D(4BHK+S)2FINISHING WORK IN PROGRESS
4E(4BHK+S)14FINISHING WORK IN PROGRESS
4F(4BHK+S)11FINISHING WORK IN PROGRESS
3L(3BHK+S)7FINISHING WORK IN PROGRESS
3M(3BHK+S)1FINISHING WORK IN PROGRESS
3N(3BHK+S)17FINISHING WORK IN PROGRESS
3O(3BHK+S)9FINISHING WORK IN PROGRESS
3P(3BHK+S)16FINISHING WORK IN PROGRESS
4A(4BHK+S)16FINISHING WORK IN PROGRESS
4B(4BHK+S)19FINISHING WORK IN PROGRESS
4C(4BHK+S)0FINISHING WORK IN PROGRESS
4D(4BHK+S)2FINISHING WORK IN PROGRESS
4E(4BHK+S)14FINISHING WORK IN PROGRESS
4F(4BHK+S)11FINISHING WORK IN PROGRESS


30-11-2011
30-06-2020
30-06-2020
30-11-2011
17.09
30-06-2020


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
30-11-2011
0
30-04-2020


334
59
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments14408
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments305630
Shops00
Plots00

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments596819904626
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments678576
Shops00
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements201.28
Water Supply System0
Sewerage treatment & garbage disposal5.70
Electricity Supply System0
Storm Water Drainage20
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other70.06

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3434
Water Supply System00
Sewerage treatment & garbage disposal5.545.54
Electricity Supply System00
Storm Water Drainage5.125.12
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other22.6822.68

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements34343434
Water Supply System0000
Sewerage treatment & garbage disposal5.545.545.545.54
Electricity Supply System050100150
Storm Water Drainage5.125.125.125.12
Parks and Playgrounds0000
Clubhouse/community centres005050
Shopping area0000
Other22.6822.6822.6822.68
Security System101010
Street Light5

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3434
Water Supply System00
Sewerage treatment & garbage disposal5.545.54
Electricity Supply System200220.61
Storm Water Drainage5.125.12
Parks and Playgrounds66.36
Clubhouse/community centres100150
Shopping area00
Other22.6822.68
Security System2527.53
Street Light1015












Particulars Remarks, if any
i. No. of Flats/Apartments constructed262Finishing work in progress
ii. No. of Flats/ Apartments booked120
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter12460.41 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter10178.18 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2282.23 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter201.63 Lakhs
vii. Amount invested in the project upto the date of application20257.24 Lakhs
Land cost (If any)478.70 Lakhs
Apartments14408.29 Lakhs
Infrastructure297.04 Lakhs
EDC/ Taxes Etc.5073.21 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession10258.52 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS473.30201.28
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE60.9220
IV. ELECTRICITY SUPPLY SYSTEM720.610
V. SEWAGE TREATMENT & GARBAGE DISPOSAL50.025.7
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER30.000
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE350.000
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.12.360
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM82.530
XVII. OTHER FACILITIES AS PER PROJECT REPORT251.5070.06









Yes
Yes
HDFC BANK, GROUND FLOOR, JEHANGIR BUILDING, M.G. ROAD, FORT MUMBAI-400001
57500000322968
HDFC0000060
400240015
60
Mr. Vijay Gupta and Mr. Amit Gupta Address : C-3/260, Janakpuri, New Delhi-110058
No Default











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. AIRPORT HEIGHT CLERANCEALREADY BEEN OBTAINED20-09-2010
II. WET CONSTRUCTIONALREADY BEEN OBTAINED24-09-2012
III. ELECTRICAL LOAD AVAILABILITY ALREADY BEEN OBTAINED22-07-2012
IV. TREE CUTTINGALREADY BEEN OBTAINED27-10-2010
V. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED15-10-2013
VI. CONSENT TO ESTABLISHALREADY BEEN OBTAINED15-04-2011
VII. FIRE SCHEME APPROVAL ALREADY BEEN OBTAINED29-07-2013
VIII. APPROVAL OF SERVICE PLAN ESTIMATEALREADY BEEN OBTAINED21-03-2014
IX. ROAD ACCESS WITH IN PWD ALREADY BEEN OBTAINED27-01-2011
X. ARAVALLIALREADY BEEN OBTAINED30-01-2013








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE IN DRAWING HALL CERAMIC TILE IN TOILET, BALCONY & KITCHEN
2WALL FINISHING DETAILSOBD IN CEILING, ACRYLIC EMULSION IN WALL
3KITCHEN DETAILSCERAMIC TILE IN FLOOR, GRANITE ON COUNTER, SS SINK
4BATHROOM FITTINGSC. P. FITTINGS & CHINAWARE
5WOOD WORK ETCWOODEN FRAME & FLUSH DOORS
6DOORS AND WINDOS FRAMESUPVC DOOR WINDOWS
7GLASS WORKGLAZED DOOR WINDOWS
8ELECTRIC FITTINGSSWITCH SOCKET, MCB & DB BOXES
9CONDUCTING AND WIRING DETAILSFRLS WIRE & PVC CIBDUIT
10CUPBOARD DETAILSNA
11WATER STORAGERCC TANK
12LIFT DETAILS10-15 PASSENGER 1-1.5M / SEC SPEED
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSUPVC DOOR WINDOWS
14DOORS WOODEN DOOR
14.1MAIN DOORSSOLID WOODEN FLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGONLY PROVISION FOR SPLIT/WINDOW A.C.
16ELECTRICAL FITTINGSLIGHT FITTINGS IN COMMON AREA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURED PAINT
20INTERNAL FINISHINGOBD ON CEILING & ACRYLIC EMULSION ON WALL, WHITE WASH IN BASEMENT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSACRYLIC EMULSION
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN EMULSION
2 . 2 WALLSACRYLIC EMULSION
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE
3 . 2 WALLSCERAMIC TILE 300 X 600 MM
3 . 3 CEILINGOBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSC.P. FIXTURES CHINAWARE FITTINGS
3 . 6 FITTING/FIXTURESC.P. FIXTURES CHINAWARE FITTINGS
4 . BED ROOMS
4 . 1 FLOORWOODEN LAMINATED FLOORING
4 . 2 WALLSACRYLIC EMULSION
4 . 3 CEILINGOBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCERAMIC TILE 300 X 300 MM
5 . 2 WALLSCERAMIC TILE 300 X 600 MM
5 . 3 CEILINGOBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSC.P. FITTINGS & CHINAWARE
5 . 6 FIXTURESC.P. FITTINGS & CHINAWARE
6 . KITCHEN
6 . 1 FLOORCERAMIC TILE 300 X 300 MM
6 . 2 WALLSCERAMIC TILE 300 X 600 MM
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE, S.S. SINK
6 . 5 FIXTURESC. P. FITTINGS
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE 300 X 300 MM
7 . 2 WALLS & CEILINGCERAMIC TILE 300 X 600 MM
7 . 3 TOILETCERAMIC TILE 300 X 600 MM
7 . 4 BALCONYCERAMIC TILE 300 X 300 MM
8 . SIT-OUTS
8 . 1 FLOOR-
8 . 2 WALLS & CEILING-
8 . 3 RAILINGS-
8 . 4 FIXTURES-












Sr. No.Document DescriptionDate of Document UploadView Document
1APPLICATION FORM11-02-2020 ------
2SERVICE PLAN APPROVAL LETTER11-02-2020 ------
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT11-02-2020 View Document
4ZONING PLAN11-02-2020 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND11-02-2020 View Document
6DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD11-02-2020 View Document
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT11-02-2020 View Document
8DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.11-02-2020 View Document
9ROAD & PAVEMENT PLAN11-02-2020 ------
10SITE PLAN11-02-2020 ------
11LC IV11-02-2020 ------
12LOI11-02-2020 ------
13BR III11-02-2020 ------
14AGREEMENT TO SALE11-02-2020 ------
15SERVICE PLAN11-02-2020 ------
16SERVICES ESTIMATE APPROVED11-02-2020 ------
17ENVIRONMENT CLEARANCE APPROVAL11-02-2020 ------
18AIRPORT HEIGHT CLEARANCE11-02-2020 ------
19FIRE SCHEME APPROVAL11-02-2020 ------
20FOREST NOC11-02-2020 ------
21ELEVATION & SECTION - 411-02-2020 ------
22CHG - 111-02-2020 ------
23ELEVATION & SECTION11-02-2020 ------
24FLOOR PLAN - 311-02-2020 ------
25FAR DETAILS11-02-2020 ------
26ELEVATION & SECTION - 211-02-2020 ------
27ELEVATION & SECTION - 311-02-2020 ------
28ELEVATION & SECTION - 511-02-2020 ------
29ELEVATION & SECTION11-02-2020 ------
30FLOOR PLAN -211-02-2020 ------
31FLOOR PLAN -311-02-2020 ------
32FLOOR PLAN11-02-2020 ------
33PARKING PLAN -111-02-2020 ------
34PARKING PLAN11-02-2020 ------
35SERVICE, SEWER,STORM,WATER SUPPLY PLAN11-02-2020 ------
36IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN19-12-2019 View Document
37A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS19-12-2019 View Document
38SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN26-12-2019 View Document
39IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN26-12-2019 View Document
40DEMARCATION PLAN11-02-2020 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Project Continuation- RC/REP/HARERA/GGM/19 of 2018 /7(3)/2022/2 dated 09.08.2022 29-09-2022 View Document