As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
33847
17-07-2017
1426000
HDFC
HRERA Gurugram
5.91875 (Acre)
1.50
1.48
5.91875 (Acre)
34 of 2014 dated 12.06.2014
Yes
31062 Lakhs
8702 Lakhs
14464 Lakhs
641 Lakhs
7255 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
2.277
4
PAVEMENTS
0.624
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
1.498
7
VEHICLE PARKINGS
0.549
8
ELECTRICITY SUB-STATION
0.038
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.927
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
5.913
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
MCG/HUDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
MCG/HUDA
No
STORM WATER DRAINAGE
MCG/HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
125
YET TO BE PREPARED
3
STORM WATER DRAINAGE
45
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
550
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
80
YET TO BE PREPARED
6
STREET LIGHTING
35
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
660
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
100
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
24-08-2017 (date)
24-08-2017 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL/COMMERCIAL
0
396
76
320
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
RETAIL/COMMERCIAL
320
NEED TO CHECK AS THE SOLD APARTMENTS ARE MORE THAN THE SOLD
15-02-2018
13-09-2023
13-09-2023
15-02-2018
42
13-09-2023
-
-
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
320
0
15-02-2018
42
13-09-2023
893
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
12928
14099
14823
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
125
Sewerage treatment & garbage disposal
80
Electricity Supply System
550
Storm Water Drainage
45
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
6.25
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
55.0
Storm Water Drainage
0
2.25
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
396
ii. No. of Flats/ Apartments booked
320
till Dec
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
14099 Lakhs
Land cost (If any)
8702 Lakhs
Apartments
0 Lakhs
Infrastructure
3455 Lakhs
EDC/ Taxes Etc.
7255 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
16963 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
ROC Attached
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
0
0
II. WATER SUPPLY SYSTEM
125
0
III. STORM WATER DRAINAGE
45
0
IV. ELECTRICITY SUPPLY SYSTEM
550
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
80
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
Yes
DLF CYBER CITY , GURUGRAM
017266200000051
YESB0000172
110532042
000172
ELAN BUILDCON PVT. LTD.
The certificate has been enclosed stating that there is no default.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. BUILDING PLAN
ALREADY BEEN OBTAINED
24-08-2017
II. APPROVAL OF SERVICE ESTIMATE
YET TO FILE FOR APPROVAL
NA
III. APPROVAL OF FIRE SCHEME
YET TO FILE FOR APPROVAL
NA
IV. FIRE NOC
YET TO FILE FOR APPROVAL
NA
V. OCCUPATION CERTIFICATE
YET TO FILE FOR APPROVAL
NA
Yes
Yes
-
ELAN TOWN CENTRE, SECTOR 67 , VILLAGE BADSHAHPUR GURUGRAM
2
438
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14464
0
6020
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
3800
0
187
12337 Lakhs
26677 Lakhs
0 Lakhs
0 Lakhs
No
13-09-2022
13-09-2022
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES
2
WALL FINISHING DETAILS
OBD
3
KITCHEN DETAILS
KITCHEN ATE COUNTER GRANITE & PLY CABINET WITH LAMINATE FINISH
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT