Quarterly Schedules

HRERA Panchkula
Project Registration Number : HRERA-PKL-FBD-145-2019
Project Name : HAPPY HOMES PRIDE
Project Number : RERA-PKL-606-2019
Project Type : NEW
Report Online Submission Date : 06-Apr-2020
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)5972
2Estimated cost of construction of apartments7500
3Estimated cost of infrastructure & other structure1173
4Other cost including EDC taxes, levies, etc2500
Total17145



Name of the approvalStatusDate
Layout PlanHave not applied till dateN/A
Demarcation PlanHave not applied till dateN/A
Zoning PlanHave not applied till dateN/A
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A



Name of the approvalStatusDate
Demarcation PlanObtained Approval on23-01-2019
Zoning PlanObtained Approval on13-02-2020
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on24-09-2019
Building PlansObtained Approval on24-09-2019
FIre NOCHave not applied till dateN/A
Total Expenditure on the project1173
Expenditure made upto the date of Registration229.40



EDC due as on the date of Registration150

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments496.62
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates16.69
5Any other receipt0
Total513.31



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure7.71
3Other costs including EDC, taxes, etc221.69
Total229.40
Balance283.91



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account513.32
3Amount withdrawn during the quarter229.41
4Balance at the end of the quarter283.91
Total Apartments in the colony796
Apartments sold upto the date of Registration269



S.No.Type/SizeApartments Sold in the Quarter
13BHK269



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure7.71
2Apartments0
3EDC, IDC, etc168.86
4Others Expenditure52.83



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date155
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 06-04-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 06-04-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 06-04-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 06-04-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 06-04-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance283.91
2Amount collected from allottees against booked plots and/or apartments899.09
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total1183



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments24.98
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc0
Total24.98
Balance1061.76



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter283.91
2Amount deposited in Escrow Account899.09
3Amount withdrawn during the quarter121.24
4Balance at the end of the quarter1061.76
Total Apartments in the colony796
Apartments sold upto the date of Registration388



S.No.Type/SizeApartments Sold in the Quarter
13BHK85
21 BHK34



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments24.98
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date87.79
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 11-04-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 11-04-2020  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 11-04-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 11-04-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 11-04-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1061.76
2Amount collected from allottees against booked plots and/or apartments107.42
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt15.66
Total1184.84



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc0
Total0
Balance1184.84



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1061.76
2Amount deposited in Escrow Account123.08
3Amount withdrawn during the quarter0
4Balance at the end of the quarter1184.84
Total Apartments in the colony796
Apartments sold upto the date of Registration388



S.No.Type/SizeApartments Sold in the Quarter
13BHK0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date155.00
2EDC due as on date87.79
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 26-09-2020  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 26-09-2020  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 26-09-2020  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 26-09-2020  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 26-09-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1184.84
2Amount collected from allottees against booked plots and/or apartments173.81
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total1358.65



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments21.23
2Expenditure on infrastructure & other structure20.32
3Other costs including EDC, taxes, etc0
Total41.55
Balance1317.10



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1184.84
2Amount deposited in Escrow Account173.81
3Amount withdrawn during the quarter41.55
4Balance at the end of the quarter1317.10
Total Apartments in the colony796
Apartments sold upto the date of Registration388



S.No.Type/SizeApartments Sold in the Quarter
13BHK0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments21.23
3EDC, IDC, etc0
4Others Expenditure20.32



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date155.00
2EDC due as on date181.45
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 30-11-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 30-11-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 30-11-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 30-11-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 30-11-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1317.10
2Amount collected from allottees against booked plots and/or apartments239.73
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt10.68
Total1567.51



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments211.62
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc69.29
Total280.91
Balance1286.60



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1317.10
2Amount deposited in Escrow Account250.41
3Amount withdrawn during the quarter280.91
4Balance at the end of the quarter1286.60
Total Apartments in the colony796
Apartments sold upto the date of Registration388



S.No.Type/SizeApartments Sold in the Quarter
1NIL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments211.62
3EDC, IDC, etc0
4Others Expenditure69.29



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date155
2EDC due as on date171.92
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 20-05-2021  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 20-05-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 20-05-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 20-05-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 20-05-2021  View