Quarterly Schedules | ||
HRERA Panchkula | ||
Project Registration Number : HRERA-PKL-FBD-146-2019 | ||
Project Name : PROPEX CITY FARIDABAD | ||
Project Number : RERA-PKL-572-2019 | ||
Project Type : NEW | ||
Report Online Submission Date : 18-Feb-2020 |
S.No. | Particulars | Amount (In Lakhs) |
1 | Cost of the land (if included in the estimated cost) | 1256.54 |
2 | Estimated cost of construction of apartments | 0 |
3 | Estimated cost of infrastructure & other structure | 483.38 |
4 | Other cost including EDC taxes, levies, etc | 835.92 |
Total | 2575.84 |
Name of the approval | Status | Date |
Layout Plan | Obtained Approval on | 01-08-2019 |
Demarcation Plan | Obtained Approval on | 13-09-2019 |
Zoning Plan | Obtained Approval on | 06-11-2019 |
Service Plans | Have not applied till date | N/A |
Electricity Plans | Have not applied till date | N/A |
Total Expenditure on the project | 1319.30 |
Expenditure made upto the date of Registration | 300.53 |
EDC due as on the date of Registration | 148.54 |
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 3.37 |
2 | Amount collected from allottees against booked plots and/or apartments | 53.68 |
3 | Amount availed from the bank/financial institutions | 0.00 |
4 | Amount contributed by the promoters/his associates | 0.00 |
5 | Any other receipt | 0.00 |
Total | 57.05 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 28.30 |
3 | Other costs including EDC, taxes, etc | 25.00 |
Total | 53.30 | |
Balance | 3.75 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 76.68 |
3 | Amount withdrawn during the quarter | 76.68 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 76.08 | 1 |
2 | 89.67 | 2 |
3 | 90.11 | 1 |
4 | 96.82 | 1 |
5 | 97.29 | 4 |
6 | 97.35 | 4 |
7 | 110.31 | 8 |
8 | 118.78 | 2 |
9 | 127.95 | 1 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 14.18 |
2 | Apartments | 0.00 |
3 | EDC, IDC, etc | 25.00 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 148.54 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 3.75 |
2 | Amount collected from allottees against booked plots and/or apartments | 106.60 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 0 |
5 | Any other receipt | 0 |
Total | 110.35 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 90.76 |
3 | Other costs including EDC, taxes, etc | 11 |
Total | 101.76 | |
Balance | 8.59 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 152.28 |
3 | Amount withdrawn during the quarter | 152.28 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 97.29 | 7 |
2 | 96.88 | 1 |
3 | 97.35 | 4 |
4 | 134.16 | 1 |
5 | 118.78 | 1 |
6 | 110.31 | 2 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 2.53 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 148.54 |
4 | Others Expenditure | 149.46 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 148.54 |
2 | EDC due as on date | 74.27 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 8.59 |
2 | Amount collected from allottees against booked plots and/or apartments | 36.53 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -1.65 |
5 | Any other receipt | 0 |
Total | 43.47 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 35.08 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 35.08 | |
Balance | 8.39 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 52.19 |
3 | Amount withdrawn during the quarter | 52.19 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 6 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 148.54 |
2 | EDC due as on date | 445.62 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 8.39 |
2 | Amount collected from allottees against booked plots and/or apartments | 88.16 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 10.00 |
5 | Any other receipt | 0.01 |
Total | 106.55 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 80.46 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 80.46 | |
Balance | 26.09 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 128.19 |
3 | Amount withdrawn during the quarter | 128.19 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 1 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 266.12 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 184.54 |
4 | Others Expenditure | 151.20 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 148.54 |
2 | EDC due as on date | 445.62 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 26.10 |
2 | Amount collected from allottees against booked plots and/or apartments | 282.55 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -18.00 |
5 | Any other receipt | -130.63 |
Total | 160.03 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 70.67 |
3 | Other costs including EDC, taxes, etc | 66.80 |
Total | 137.47 | |
Balance | 22.56 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 426.64 |
3 | Amount withdrawn during the quarter | 426.64 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 11 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 352.34 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 251.34 |
4 | Others Expenditure | 151.20 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 148.54 |
2 | EDC due as on date | 445.62 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 22.56 |
2 | Amount collected from allottees against booked plots and/or apartments | 473.22 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -35.30 |
5 | Any other receipt | 121.17 |
Total | 581.65 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 63.11 |
3 | Other costs including EDC, taxes, etc | 457.00 |
Total | 520.11 | |
Balance | 61.54 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 690.69 |
3 | Amount withdrawn during the quarter | 690.69 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 14 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 443.10 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 708.34 |
4 | Others Expenditure | 151.20 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 61.54 |
2 | Amount collected from allottees against booked plots and/or apartments | 210.32 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -70.00 |
5 | Any other receipt | 10.30 |
Total | 212.17 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 131.41 |
3 | Other costs including EDC, taxes, etc | 74.75 |
Total | 206.16 | |
Balance | 6.00 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 332.38 |
3 | Amount withdrawn during the quarter | 332.38 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 2 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 521.99 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 151.20 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 6.00 |
2 | Amount collected from allottees against booked plots and/or apartments | 123.90 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -50.00 |
5 | Any other receipt | 0 |
Total | 79.90 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 43.11 |
3 | Other costs including EDC, taxes, etc | 25.37 |
Total | 68.48 | |
Balance | 11.42 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 199.66 |
3 | Amount withdrawn during the quarter | 199.66 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 2 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 604.23 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 11.42 |
2 | Amount collected from allottees against booked plots and/or apartments | 36.47 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 0 |
5 | Any other receipt | 0 |
Total | 47.89 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 21.43 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 21.43 | |
Balance | 26.46 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 52.10 |
3 | Amount withdrawn during the quarter | 52.10 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 1 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 699.61 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 26.46 |
2 | Amount collected from allottees against booked plots and/or apartments | -0.37 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -3.65 |
5 | Any other receipt | -4.05 |
Total | 22.44 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 20.48 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 20.48 | |
Balance | 1.97 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 0 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 0 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 729.37 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 1.97 |
2 | Amount collected from allottees against booked plots and/or apartments | 0 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -1.50 |
5 | Any other receipt | 0 |
Total | 0.47 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 0 | |
Balance | 0.47 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 0 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 0 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 752.00 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0.47 |
2 | Amount collected from allottees against booked plots and/or apartments | 0 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -0.21 |
5 | Any other receipt | 0 |
Total | 0.26 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 0 | |
Balance | 0.26 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 0 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 0 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 752.00 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0.26 |
2 | Amount collected from allottees against booked plots and/or apartments | 73.17 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 0 |
5 | Any other receipt | 0 |
Total | 73.43 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 22.47 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 22.47 | |
Balance | 50.95 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 104.52 |
3 | Amount withdrawn during the quarter | 104.52 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 10 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 926.70 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 50.95 |
2 | Amount collected from allottees against booked plots and/or apartments | 651.46 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -606.00 |
5 | Any other receipt | -14.99 |
Total | 81.42 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 0 |
2 | Expenditure on infrastructure & other structure | 80.46 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 80.46 | |
Balance | 0.96 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 935.15 |
3 | Amount withdrawn during the quarter | 935.15 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 136 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | PLOT | 29 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Apartments Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Garages Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 928.94 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 783.09 |
4 | Others Expenditure | 176.57 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|