HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-946-2021
Submission Date : 28-07-2021 08:29:09 AM
Applicant Type : Company
Project Type: NEW




NEW ERA INFRASTRUCTURE PRIVATE LIMITED
FLAT NO. 711, GURU CO-OPERATIVE GROUP HOUSING SOCIETY, ROHINI, SECTOR-14, DELHI-110085
9813957448 (Number Shared by Promoter in Public)
guliaapex@gmail.com
XXXX878N
U45201DL2003PTC123427
 
 


 
 


 
 


 
 







SOUTH CITY
VILLAGE AHMADPUR, SECTOR-27
SONIPAT
SONIPAT
9813957448 (Number Shared by Promoter in Public)
guliaapex@gmail.com
VINOD KUMAR GULIA
9813957448 (Number Shared by Promoter in Public)
guliaapex@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
170550526-07-2021250000THE FEDERAL BANK LIMITEDHRERA Panchkula







5.456 (Acre)
0
0
5.456 (Acre)
37 OF 2021, DATED 16.07.2021 granted by DTCP, Haryana
Yes







2219.79 Lakhs
1364.00 Lakhs
0 Lakhs
370.66 Lakhs
485.13 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD3.024
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS0.980
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.546
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.002
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.111
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.546
12ANY OTHER0
13CONSTRUCTION OF COMMERCIAL SHOPS PLOTTED0.178
14UGT0.062
15MILK AND VEG BOOTH0.007
Total5.456




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS78.52AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM35.85AS PER PROJECT REPORT
3STORM WATER DRAINAGE28.82AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM84.04AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL44.07AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS14.83AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER6.80AS PER PROJECT REPORT
15BOUNDARY WALL GATE AND GUARD ROOM77.72AS PER PROJECT REPORT


20-07-2021 (date)
NA (date)
01-10-2021
15-07-2026
Plot Area(In Square Meter)Number of plots in the project
132.3060
110.2539
720.371


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.72
Water Supply System3.98
Sewerage treatment & garbage disposal4.90
Electricity Supply System9.34
Storm Water Drainage3.20
Parks and Playgrounds1.65
Clubhouse/community centres0
Shopping area0
Other0.76

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.72
Water Supply System3.98
Sewerage treatment & garbage disposal4.90
Electricity Supply System9.34
Storm Water Drainage3.20
Parks and Playgrounds1.65
Clubhouse/community centres0
Shopping area0
Other0.76
Boundary Wall Gate and Guard Room8.64












Yes
No
THE FEDERAL BANK LTD., KUNDLI, SONEPAT.
21160200001490
FDRL0002116
110049036
2116
MR. VINOD KUMAR R/O HO. NO. 403, SECTOR-15, SONEPAT, HARYANA. MOBILE NO. 9813957448
YES











Yes
No
No
No
No
No
No
No
No
No


Yes
No
No
No
No
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE ALREADY BEEN OBTAINED16-07-2021
II. LAYOUT PLANALREADY BEEN OBTAINED20-07-2021








Yes


Yes


FULL AGREEMENT IS IMPORTANT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND22-07-2021 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-07-2021 View Document
3DEMARCATION PLAN27-07-2021 View Document
4ZONING PLAN27-07-2021 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-07-2021 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS27-07-2021 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-07-2021 View Document
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD27-07-2021 View Document
9CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-07-2021 View Document
10DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.27-07-2021 View Document
11CASH FLOW STATEMENT OF THE PROPOSED PROJECT27-07-2021 View Document